Job No.: TCS00694/13

 

 

 

 

 

 

 

 

 

Agreement No. CE 45/2008 (CE)

Liantang/Heung Yuen Wai

Boundary Control Point and Associated Works

 

 

 

 

 

 

 

 

 

Monthly Environmental Monitoring and Audit Report (No.65) – December 2018

 

 

 

 

 

 

 

 

Prepared For

 

 

 

 

Civil Engineering and Development Department (CEDD)

 

 

 

 

 

 

 

 

 

 

 

Date

Reference No.

Prepared By

Certified By

14 January 2019

TCS00694/13/600/R1936v2

Nicola Hon

 (Environmental Consultant)

Tam Tak Wing

(Environmental Team Leader)

 

Version

Date

Remarks

1

9 January 2019

First Submission

2

14 January 2019

Amended according to the IEC’s comments on 10 January 2019

 

 

 

 

 

 


 

 

 

 

executive summary

ES01            This is the 65th monthly EM&A report presenting the monitoring results and inspection findings for the reporting period from 1 to 31 December 2018 (hereinafter ‘the Reporting Period’).

Environmental Monitoring and Audit Activities

ES02            To facilitate the project management and implementation, Liantang/Heung Yuen Wai Boundary Control Point and Associated Works of the Project is divided to seven CEDD contracts including Contract 2 (CV/2012/08), Contract 3 (CV/2012/09), Contract 4 (NE/2014/02), Contract 5 (CV/2013/03), Contract 6 (CV/2013/08) and Contract 7 (NE/2014/03) and an ArshSD contract (Contract SS C505).

ES03            In the Reporting Period, the major construction works under Liantang/Heung Yuen Wai Boundary Control Point and Associated Works of the Project included Contract 2, Contract 3, Contract 4, Contract 6, Contract 7 and Contract SS C505.  Environmental monitoring activities under the EM&A programme in the Reporting Period are summarized in the following table.

Environmental Aspect

Environmental Monitoring Parameters / Inspection

Reporting Period

Number of Monitoring Locations to undertake

Total Occasions 

Air Quality

1-hour TSP

9

135

24-hour TSP

9

50

Construction Noise

Leq(30min) Daytime

10

40

Water Quality

Water in-situ measurement and/or sampling

WM1 & WM1-C

14 Scheduled & 0 extra

WM2A(a) & WM2A-Cx

14 Scheduled & 0 extra

WM2B & WM2B-C

14 Scheduled & 0 extra (*)

WM3x &WM3-C

14 Scheduled & 0 extra

WM4, WM4-CA &WM4-CB

14 Scheduled & 0 extra

Ecology

Woodland compensation

i)      General Health condition of planted species

ii)     Survival of planted species

9 Quadrats and transect

0

Joint Site Inspection / Audit

IEC, ET, the Contractor and RE joint site Environmental Inspection and Auditing

Contract 2

4

Contract 3

4

Contract 4

4

Contract 6

4

Contract 7

4

Contract SS C505 (#)

4

Remark: (#) IEC only joined one (1) event of site inspection for Contract SS C505.

             (*) In the whole Reporting Period, water sampling was unable to carry out at WM2B and WM2B-C due to shallow water (water depth under 150mm)  

 

Action and Limit (A/L) Levels exceedance

ES04            In the Reporting Period, no construction noise exceedance and valid noise complaint was recorded. For air quality monitoring, no exceedance of 1-hour and 24-hour TSP was recorded. Moreover, no exceedance was recorded during water quality monitoring.  The summary of exceedance in the Reporting Period is shown below.

Environmental Aspect

Monitoring Parameters

Action Level

Limit Level

Event & Action

NOE Issued

Investigation Result

Project related exceedance

Corrective Actions

Air Quality

1-hour TSP

0

0

0

--

--

--

24-hour TSP

0

0

0

--

--

--

Construction Noise

Leq(30min) Daytime

0

0

0

--

--

--

Water Quality

DO

0

0

0

--

--

--

Turbidity

0

0

0

--

--

--

SS

0

0

0

 

Environmental Complaint

ES05            In this Reporting Period, two (2) documented environmental complaints were received regarding the dust concerns and cleanliness of Lin Ma Hang Road in relation to the works under Contract 6 and Contract SS C505 respectively.  Investigation report for the dust concerned under Contract 6 was completed and concluded not project related. Investigation report for the complaint for SS C505 is underway by ET. 

ES06            In addition, EPD’s recently ambush operation in Wo Keng Shan Road revealed that a dump truck carrying dusty construction waste materials from LT/HYW- C6 travelling to NENT Landfill on 14 December 2018 without proper cover.  A warning letter has been sent to the Contractor (CCKJV). To prevent recurrence of the case, CCKJV rejected the subject dump truck and the related driver from entering the site to perform the disposal activities effective immediately.  Also, specific training was provided to the representative of sub-contractor and urged him to convey the message to all of their dump truck drivers that the mechanical cover of the dump truck should be maintained fully close for the whole trip of the dumping activities.  To ensure the mechanical cover shall be covered properly before leaving the Site, the CHIT will only provide to the dump truck driver after checked the mechanical cover has been covered properly at site exit.

Notification of Summons and Successful Prosecutions

ES07            No environmental summons and prosecutions were recorded in the Reporting Period. 

Reporting Change

ES08            No reporting changes were made in the Reporting Period.

Site Inspection

ES09            In this Reporting Period, joint site inspection to evaluate the site environmental performance at Contract 2 has been carried out by the RE, IEC, ET and the Contractor on 7, 14, 21 and 28 December 2018.  No non-compliance was noted during the site inspection. 

ES10            In the Reporting Period, joint site inspection to evaluate the site environmental performance at Contract 3 has been carried out by the RE, IEC, ET and the Contractor on 5, 13, 19 and 27 December 2018.  No non-compliance was noted during the site inspection. 

ES11            In the Reporting Period, joint site inspection to evaluate the site environmental performance at Contract 4 has been carried out by the RE, IEC, ET and the Contractor on 7, 14, 17 and 28 December 2018.  No non-compliance was noted.  

ES12            In the Reporting Period, joint site inspection to evaluate the site environmental performance at Contract 6 has been carried out by the RE, IEC, ET and the Contractor on 6, 13, 20 and 27 December 2018.  No non-compliance was noted during the site inspection. 

ES13            In the Reporting Period, joint site inspection for Contract 7 to evaluate the site environmental performance has been carried out by the RE, IEC, ET and the Contractor on 7, 14, 18 and 28 December 2018.  No non-compliance was noted during the site inspection. 

ES14            In the Reporting Period, joint site inspection to evaluate the site environmental performance at Contract SS C505 has been carried out by the RE, ET and the Contractor on 5, 12, 19 and 24 December 2018 in which IEC joined the site inspection on 19 December 2018.  No non-compliance was noted during the site inspection.

Future Key Issues

ES15            During dry season, special attention should be paid on the potential construction dust impact since most of the construction sites are adjacent to villages. The Contractor should fully implement the construction dust mitigation measures as appropriately.

ES16            Preventive measures for muddy water or other water pollutants from site surface flow to local stream such as Kong Yiu Channel, Ma Wat Channel, Ping Yuen River, Kwan Tei River or public area should be properly maintained.  The Contractors should paid special attention on water quality mitigation measures and fully implement according ISEMM of the EM&A Manual, in particular for working areas near Ma Wat Channel and Ping Yuen River.

ES17            In addition, all effluent discharge shall be ensure to fulfill Technical Memorandum of Effluent Discharged into Drainage and Sewerage Systems, inland and Coastal Waters criteria or discharge permits stipulation.

ES18            Construction noise would be a key environmental issue during construction work of the Project.  Noise mitigation measures such as using quiet plants should be implemented in accordance with the EM&A requirement.

ES19            Since most of construction sites under the Project are located adjacent to villages, the Contractors should fully implement air quality mitigation measures to reduce construction dust emission.

 

 

 

 

 


Table of Contents

1     Introduction   1

1.1            Project Background   1

1.2            Report Structure  1

2     Project Organization and Construction progress  3

2.1            Construction Contract Packaging   3