Job No.: TCS00694/13

 

 

 

 

 

 

 

 

 

Agreement No. CE 45/2008 (CE)

Liantang/Heung Yuen Wai

Boundary Control Point and Associated Works

 

 

 

 

 

 

 

 

 

18th Quarterly Environmental Monitoring & Audit Summary Report –

(November 2017 to January 2018)

 

 

 

 

 

Prepared For

 

 

 

 

 

Civil Engineering and Development

Department (CEDD)

 

 

 

 

 

 

 

 

 

Quality Index

Date

Reference No.

Prepared By

Certified By

26 April 2018

TCS00694/13/600/R1510v2

Nicola Hon

(Environmental Consultant)

T.W. Tam

(Environmental Team Leader)

 

 

 

Version

Date

Description

1

24 April 2018

First Submission

2

26 April 2018

Amended according to the IEC’s comment on 25 April 2018

 

 

 

 

 

 

This report has been prepared by Action-United Environmental Services & Consulting with all reasonable skill, care and diligence within the terms of the Agreement with the client, incorporating our General Terms and Conditions of Business and taking account of the resources devoted to it by agreement with the client. We disclaim any responsibility to the client and others in respect of any matters outside the scope of the above. This report is confidential to the client and we accept no responsibility of whatsoever nature to third parties to whom this report, or any part thereof, is made known. Any such party relies upon the report at their own risk.

 


 

 

 

 

 

Executive Summary

ES.01.   This is the 18th Quarterly EM&A Summary Report for the “Liantang/Heung Yuen Wai Boundary Control Point and Associated Works” under Environmental Permit No. EP-404/2011/D (hereinafter ‘‘the EP’’), covering the period from 1 November 2017 to 31 January 2018 (hereinafter “Reporting Period”).

 

Environmental Monitoring and Audit Activities

ES.02.   In the Reporting Period, the construction works under Liantang/Heung Yuen Wai Boundary Control Point and Associated Works of the Project included Contract 2, Contract 3, Contract 6, Contract 7 and Contract SS C505.  Environmental monitoring activities under the EM&A programme in the Reporting Period are summarized in the following table.

 

Environmental Aspect

Monitoring Parameters / Inspection

Reporting Period

Monitoring Locations / Contracts

Total Occasions  

Air Quality

1-hour TSP

9

432

24-hour TSP

9

144

Construction Noise

Leq(30min) Daytime

10

130

Water Quality

Water in-situ measurement and/or sampling

WM1 & WM1-C,

40 scheduled and 0 extra of sampling day

WM2A & WM2A-Cx

40 scheduled and 4 extra of sampling day

WM2B & WM2B-C

(*) 40 Scheduled

WM3 &WM3-C

40 scheduled and 2 extra of sampling day

WM4, WM4-CA &WM4-CB

40 scheduled and 6 extra of sampling day

Ecology

Woodland compensation

i)     General Health condition of planted species

ii)   Survival of planted species

9 Quadrats

1

Joint Site Inspection / Audit

IEC, ET, the Contractor and RE joint site Environmental Inspection and Auditing

Contract 2

13

Contract 3

13

Contract 4

13

Contract 6

13

Contract 7

13

Contract SS C505 (#)

14

Note: Extra monitoring day was due to measurement results exceedance

(#) IEC only joined inspection for Contract SS C505 once per month.

(*) During the whole reporting period, water sampling was unable to carry out at WM2B and WM2B-C due to shallow water (water depth under 150mm)

 

Breaches of Action/Limit levels

ES.03.   In the Reporting Period, no noise exceedance and valid noise complaint was registered for construction noise.  For air quality, there were 6 Action Level exceedances of 24-hour TSP monitoring results recorded. For water quality monitoring, a total of 26 Action/ Limit Level exceedance were recorded.  The summary of exceedance for the Reporting Period is shown below.

 

Environmental Aspect

Monitoring Parameters

Action Level

Limit Level

Event & Action

NOE Issued

Investigation

Corrective Actions

Air Quality

1-hour TSP

0

0

0

--

--

24-hour TSP

6

0

6

Not project related

NA

Construction Noise

Leq(30min) Daytime

0

0

0

--

--

Water Quality

DO

0

0

0

--

--

Turbidity

0

13

13

      6 numbers of  LL exceedances which recorded on 6, 11, 15 Dec 17 were related to the insufficient mitigation measures for Contract 3.

      Other 20 numbers of exceedances were not project related.

The Contractor was reminded to implement water quality mitigation measures in accordance with ISEMM of the EM&A Manual requirements

SS

1

12

13

 

ES.04.   Investigation Reports for all 24-hour TSP exceedances were completed by ET which concluded that the exceedances were not project related.  According to the observation during site audit, the Contractor had properly implemented the dust mitigation measures such as provided water spraying on construction area and site haul road regularly.  Moreover, water tanker and road sweeper were deployed the main road on regular basis to suppress fugitive dust and remover dirt and debris on road.  It was considered that the exceedances were likely related to the dust impact from traffic.

 

ES.05.   Investigation Reports for all water quality exceedances were completed by ET.  The investigation result revealed that the LL exceedances on 6, 11, 15 December 2017 were related to the insufficient water quality mitigation measures for Contract 3 while the other exceedances was not project-related.  As remedial action, the relevant Contractor had enhanced the water quality mitigation measures such as covering the exposed area by tarpaulin sheet to minimize muddy runoff and no project-related exceedance was recorded after the enhancement measures.

 

Environmental Complaint

ES.06.   In this Reporting Period, four (4) documented environmental complaint was received regarding the air quality and noise issues under the EM&A Programme.  Subsequent joint site inspection was carried out for complaint investigation and investigation reports were submitted by ET after reviewed by IEC.  The IRs revealed that the Contractors have properly implemented the mitigation measures and no breaches of EM&A programme was seen.  Further enhancement measures were included and implemented in response to the complaint.  

 

Notification of Summons and Successful Prosecutions

ES.07.   No environmental summons or successful prosecutions were recorded in the Reporting Period.

 

Reporting Changes

ES.08.   No reporting changes were made in the Reporting Period.

 

Future key issues

ES.09.   During dry season, special attention should be paid on the potential construction dust impact since most of the construction sites are adjacent to villages. The Contractor should fully implement the construction dust mitigation measures as appropriately.

 

ES.10.   Preventive measures for muddy water or other water pollutants from site surface flow to local stream such as Kong Yiu Channel, Ma Wat Channel, Ping Yuen River, Kwan Tei River or public area should be properly maintained.  The Contractors should paid special attention on water quality mitigation measures and fully implement according ISEMM of the EM&A Manual, in particular for working areas near Ma Wat Channel and Ping Yuen River.

 

ES.11.   In addition, all effluent discharge shall be ensure to fulfill Technical Memorandum of Effluent Discharged into Drainage and Sewerage Systems, inland and Coastal Waters criteria or discharge permits stipulation.

 

ES.12.   Construction noise would be a key environmental issue during construction work of the Project.  Noise mitigation measures such as using quiet plants should be implemented in accordance with the EM&A requirement.

 


Table of Contents

1       Introduction   1

1.1          Project Background   1

1.2          Report Structure  1

2       Project Organization and Construction progress  2

2.1          Construction Contract Packaging   2

2.2          Project Organization   4

2.3          Concurrent Projects  6

2.4          Construction Progress  6

2.5          Summary of Environmental Submissions  8

3       Project Organization and Construction progress  12

3.1          General  12

3.2          Monitoring Parameters  12

3.3          Monitoring Locations  12

3.4          Monitoring Frequency and Period   14

3.5          Monitoring Equipment  15

3.6          Monitoring Methodology   17

3.7          Equipment Calibration   19

3.8          Derivation of Action/Limit (A/L) Levels  19

3.9          Data Management and Data QA/QC Control  20

4       Air Quality Monitoring   21

4.1          General  21

4.2          Summary of Monitoring Results  21

5       Construction Noise Monitoring   23

5.1          General  23

5.2          Summary of Monitoring Results  23

6       Water Quality Monitoring   25

6.1          General  25

6.2          Summary of Monitoring Results  25

7       Ecology Monitoring   29

7.1          General  29

8       Waste Management   30

8.1          General Waste Management  30

8.2          Records of Waste Quantities  30

9       Site Inspections  32

9.1          requirements  32

10     Non-compliance, Complaints, Notifications of Summons and Prosecutions  35

10.1        Status of Non-compliance Environmental Complaint, Summons and Prosecution   35

11     Implementation Status of Mitigation Measures  38

11.1        General Requirements  38

12     Conclusions and Recommendations  39

12.1        Conclusions  39

12.2        Recommendations  39

 


List of tables

Table 2-1      Status of Environmental Licenses and Permits of the Contracts

Table 3-1      Summary of EM&A Requirements

Table 3-2      Impact Monitoring Stations - Air Quality

Table 3-3      Impact Monitoring Stations - Construction Noise

Table 3-4      Impact Monitoring Stations - Water Quality

Table 3-5      Air Quality Monitoring Equipment

Table 3-6      Construction Noise Monitoring Equipment

Table 3-7      Water Quality Monitoring Equipment

Table 3-8      Action and Limit Levels for Air Quality Monitoring

Table 3-9      Action and Limit Levels for Construction Noise

Table 3-10    Action and Limit Levels for Water Quality

Table 4-1     Summary of Air Quality Monitoring Results

Table 4-2      Summaries of Breaches of Air Quality A/L Levels

Table 5-1     Summary of Construction Noise Monitoring Results

Table 5-2      Summaries of Breaches of Construction Noise A/L Levels

Table 6-1      Summary of the Water Quality Monitoring Results – Contracts SS C505 & 6

Table 6-2      Summary of the Water Quality Monitoring Results – Contracts 2 & 3

Table 6-3      Summary of the Water Quality Monitoring Results – Contract 6

Table 6-4      Summary of the Water Quality Monitoring Results – Contracts 2 & 6

Table 6-5      Summaries of Breaches of the Existing Water Quality A/L Levels

Table 6-6      Summary of Water Quality Exceedance in the Reporting Period

Table 8-1      Summary of Quantities of Inert C&D Materials

Table 8-2      Summary of Quantities of C&D Wastes

Table 9-1      Summary of Reminders/Observations of Site Inspection – Contract 2

Table 9-2      Summary of Reminders/Observations of Site Inspection – Contract 3

Table 9-3      Summary of Reminders/Observations of Site Inspection – Contract 6

Table 9-4      Summary of Reminders/Observations of Site Inspection – Contract SS C505

Table 9-5      Summary of Reminders/Observations of Site Inspection – Contract 7

Table 9-6      Summary of Reminders/Observations of Site Inspection – Contract 7

Table 10-1    Statistical Summary of Environmental Complaints

Table 10-2    Statistical Summary of Environmental Summons

Table 10-3    Statistical Summary of Environmental Prosecution

Table 11-1    Environmental Mitigation Measures

 

List of Annexes

Appendix A  Layout plan of the Project

Appendix B  Environmental Management Organization Chart

Appendix C  Designated Monitoring Locations as Recommended in the Approved EM&A Manual

Appendix D  Monitoring Locations for Impact Monitoring

Appendix E  Event and Action Plan

Appendix F  Graphical Plots for Monitoring Result

Appendix G Weather information

Appendix H Waste Flow Table

Appendix I   Implementation Schedule for Environmental Mitigation Measures

 

 

 


1        Introduction

1.1  Project Background

1.1.1.      Civil Engineering and Development Department is the Project Proponent and the Permit Holder