Job No.: TCS00694/13

 

 

 

 

 

 

 

 

 

Agreement No. CE 45/2008 (CE)

Liantang/Heung Yuen Wai

Boundary Control Point and Associated Works

 

 

 

 

 

 

 

 

 

Monthly Environmental Monitoring and Audit Report (No.43) ¡V February 2017

 

 

 

 

 

 

 

 

Prepared For

 

 

 

 

Civil Engineering and Development Department (CEDD)

 

 

 

 

 

 

 

 

 

 

 

Date

Reference No.

Prepared By

Certified By

14 March 2017

TCS00694/13/600/R0887v2

Nicola Hon

 (Environmental Consultant)

Tam Tak Wing

(Environmental Team Leader)

 

Version

Date

Remarks

1

8 March 2017

First Submission

2

14 March 2017

Amended against the IEC¡Šs comments on 11 March 2017

 

 

 

 

 

 


 

 

 

 

 

executive summary

ES01            This is the 43rd monthly EM&A report presenting the monitoring results and inspection findings for the reporting period from 1 to 28 February 2017 (hereinafter ¡¥the Reporting Period¡Š).

 

Environmental Monitoring and Audit Activities

ES02            To facilitate the project management and implementation, Liantang/Heung Yuen Wai Boundary Control Point and Associated Works of the Project is divided to seven CEDD contracts including Contract 2 (CV/2012/08), Contract 3 (CV/2012/09), Contract 4 (TCSS), Contract 5 (CV/2013/03), Contract 6 (CV/2013/08) and Contract 7 (NE/2014/03) and an ArshSD contract (Contract SS C505).

 

ES03            In the Reporting Period, the major construction works under Liantang/Heung Yuen Wai Boundary Control Point and Associated Works of the Project included Contract 2, Contract 3, Contract 6, Contract 7 and Contract SS C505.  Environmental monitoring activities under the EM&A programme in the Reporting Period are summarized in the following table.

 

Environmental Aspect

Environmental Monitoring Parameters / Inspection

Reporting Period

Number of Monitoring Locations to undertake

Total Occasions  

Air Quality

1-hour TSP

9

135

24-hour TSP

9

45

Construction Noise

Leq(30min) Daytime

10

40

Water Quality

Water in-situ measurement and/or sampling

WM1 & WM1-C

12 Scheduled & 1 extra

WM2A(a) & WM2A-Cx

12 Scheduled & 2 extra

WM2B & WM2B-C

12 Scheduled & 0 extra

WM3x &WM3-C

12 Scheduled & 1 extra

WM4, WM4-CA &WM4-CB

12 Scheduled & 0 extra

Ecology

Woodland compensation

i)     General Health condition of planted species

ii)   Survival of planted species

9 Quadrats

1

Joint Site Inspection / Audit

IEC, ET, the Contractor and RE joint site Environmental Inspection and Auditing

Contract 2

4

Contract 3

5

Contract 6

4

Contract 7

5

Contract SS C505

4

Note: Extra monitoring day was due to measurement results exceedance

 

Action and Limit (A/L) Levels exceedance

ES04            In the Reporting Period, no air quality and construction noise exceedances were recorded.    For water quality monitoring, a total of thirteen (13) Limit Level exceedances were recorded.  The summary of exceedance in the Reporting Period is shown below.

 

Environmental Aspect

Monitoring Parameters

Action Level

Limit Level

Event & Action

NOE Issued

Investigation Result

Project related exceedance

Corrective Actions

Air Quality

1-hour TSP

0

0

0

--

--

--

24-hour TSP

0

0

0

--

--

--

Construction Noise

Leq(30min) Daytime

0

0

0

--

--

--

Water Quality

DO

0

0

0

-

--

--

Turbidity

0

4

4

-  Exceedances recorded at WM1 are under investigation.

-  All other NOEs were concluded as non-project related 

0

The Contractors were reminded to  implement water quality mitigation measures in accordance with ISEMM of the EM&A Manual requirements

SS

0

9

9

0

 

Environmental Complaint

ES05            In this Reporting Period, one (1) documented environmental complaint regarding noise issue for Contract 6 in January 2017 was received.  Investigation report for the complaint is in progress.  

ES06              The summary of complaint received in the Reporting Period is summarized below.

Reporting Period

Contract No

Environmental Complaint

Frequency

Complaint Nature

Project related complaint

1 ¡V 28 Feb 2017

Contract 2

0

NA

NA

Contract 3

0

NA

NA

Contract 6

1

Noise (1)

#

Contract 7

0

NA

NA

SS C505

0

NA

NA

 # The complaint is under investigation. 

Notification of Summons and Successful Prosecutions

ES07            No environmental summons or successful prosecutions were recorded in the Reporting Period.  

 

Reporting Change

ES08            In the Reporting period, no reporting changes were made.

 

Site Inspection

ES09            In this Reporting Period, joint site inspection to evaluate the site environmental performance at Contract 2 has been carried out by the RE, IEC, ET and the Contractor on 3, 10, 17 and 24 February 2017.  No non-compliance was noted during the site inspection.  

 

ES10            In the Reporting Period, joint site inspection to evaluate the site environmental performance at Contract 3 has been carried out by the RE, IEC, ET and the Contractor on 2, 6, 15, 20 and 27 February 2017.  No non-compliance was noted during the site inspection.  

 

ES11            In the Reporting Period, joint site inspection to evaluate the site environmental performance at Contract 6 has been carried out by the RE, IEC, ET and the Contractor on 2, 9, 16 and 23 February 2017.  No non-compliance was noted during the site inspection.  

 

ES12            In the Reporting Period, joint site inspection to evaluate the site environmental performance at Contract SS C505 has been carried out by the RE, IEC, ET and the Contractor on 1, 8, 15 and 22 February 2017.  No non-compliance was noted during the site inspection.  

 

ES13            In the Reporting Period, joint site inspection to evaluate the site environmental performance at Contract 7 has been carried out by the RE, IEC, ET and the Contractor on 1, 7, 14, 21 and 28 February 2017. No non-compliance was noted during the site inspection.  

 

Future Key Issues

ES14            During dry season, special attention should be paid on the potential construction dust impact since most of the construction sites are adjacent to villages. The Contractor should fully implement the construction dust mitigation measures.

 

ES15            Preventive measures for muddy water or other water pollutants from site surface flow to local stream such as Kong Yiu Channel, Ma Wat Channel, Ping Yuen River, Kwan Tei River or public area should be properly maintained.  The Contractors should paid special attention on water quality mitigation measures and fully implement according ISEMM of the EM&A Manual, in particular for working areas near Ma Wat Channel and Ping Yuen River.  Moreover, all effluent discharge shall be ensure to fulfill Technical Memorandum of Effluent Discharged into Drainage and Sewerage Systems, inland and Coastal Waters criteria or discharge permits stipulation.

 

ES16            Construction noise would be a key environmental issue during construction work of the Project.  Noise mitigation measures such as using quiet plants should be implemented in accordance with the EM&A requirement.

 

 


Table of Contents

1     Introduction   1

1.1            Project Background   1

1.2            Report Structure  1

2     Project Organization and Construction progress  3

2.1            Construction Contract Packaging   3

2.2            Project Organization   5

2.3            Concurrent Projects  7

2.4            Construction Progress  7